- Client
- A business centre in central Mumbai
- Service
- IT Networking
- Handover
- Handover report signed by the customer
A business centre in central Mumbai needed two floors recabled and its network rack replaced. The businesses on those floors had to keep working throughout.
Delta8 split the job over two weekends, one floor at a time, which left room to deal with surprises on site. The team traced and labelled the existing ports, laid the new cable runs, replaced the rack and moved the equipment across, with extra care around the server area.
The centre signed for 500 tested Cat6 connections, 150 of them new, along with 490 patch cords, 21 patch panels and a 45U open rack. Every point is labelled.